Scope and prerequisites

PC retail 1.2 series, default settings, no mods, liquid pipelines. Valve unlocks at Tier 5 Oil Processing and costs four Rubber and four Steel Beams. Treat it separately from providing head lift or increasing liquid production.

Steps and result checks

  1. Identify the intended source-to-consumer direction. Note the previous setting, supply and demand, and which branch needs a different limit.
  2. Select Valve in the build menu and attach it to the pipe. Confirm input/output orientation before completing placement; a reversed Valve blocks the intended direction.
  3. Interact with the installed Valve and set its flow ceiling, from 0.0 to 600.0 m³/min. For example, enter 60.0 and check the displayed setting. This does not command the system to deliver exactly sixty per minute.
  4. Check pipe fill and actual delivery downstream. An incompletely filled input pipe can pass less than the setting. To undo an adjustment, restore the recorded previous limit and check source and consumer again.

Troubleshooting

Limits and exceptions

One-way liquid passage does not guarantee that downstream pressure waves cannot affect the input side. Verify actual delivery rather than promising precise metering from a setting. See pumps and head lift and fluid buffers for the separate issues.

Sources and references

Questions and contributions

Submissions are currently paused. You cannot enter or send a post until reception resumes.